Elam Beiler Bid Package

Bid Details

Primary Contact

Sarah Xenophon, Project Manager

TeamAg Inc.

570-294-5229

sarahx@teamaginc.com

Scope of Work

Summary of Proposed NRCS Practice Codes

  • PA-313 Waste Storage Facility
  • PA-342 Critical Area Planting
  • PA-360 Waste Facility Closure
  • PA-367 Roofs and Covers
  • PA-382 Fencing
  • PA-391 Riparian Forested Buffer
  • PA-468 Lined Waterway or Outlet
  • PA-558 Roof Runoff
  • PA-560 Access Road
  • PA-561 Heavy Use Area Protection
  • PA-578 Stream Crossing
  • PA-587 Structure for Water Control
  • Pa-606 Subsurface Drain
  • PA-620 Underground Outlet
  • PA-634 Manure Transfer
  • PA-362 Diversion

All work to be done in accordance with the Pennsylvania Technical Guide (PATG) NRCS standards and construction specifications.

Site Photos

Bid & Contracting Requirements

Schedule

Mandatory Pre-bid Site Showing: November 20th, 9am – 208 Rosedale Rd, Christiana, PA 17509

Bids Due: December 6th, by 4:00pm 

Bid Opening Date/Time: December 10th, 10am – online and in-person 120 Lake Street, Ephrata, PA 17901

Construction: expected completion by 12/31/25

Wage Requirements

This project requires the use of Prevailing Wages. Please find the prevailing wage determination for this project linked below.

https://www.dlisecureweb.pa.gov/PrevWage/Pages/Project.aspx?ID=188189&PageType=

Contracting Details

  1. This project shall be awarded as a single contract to a primary GC, using subcontractors as needed.

  2. Prior to signing contracts, successful contractors will be required to provide the following:
    1. Certificate of insurance based on the services or product provided
    2. Proof of registration with the Commonwealth of Pennsylvania
    3. Performance and Payment Bonds
  3. TeamAg, Inc. will manage the construction of this project and perform inspections during construction to ensure that construction is done in accordance with the drawings and specifications.
  4. Contractors are to provide invoices and Prevailing Wage certifications ( LLC-25) to TeamAg, Inc. (sarahx@teamaginc.com) on a monthly basis.
  5. Construction is expected to start within 90 days of the contract being awarded and is expected to be completed by 12/31/25.
  6. All subcontractors engaged by primary contractors must follow all the provisions of primary contractors.
  7. Upon completion of the contracted work, contractors shall sign a Certification of Performance that all work was performed according to the design drawings, specifications, and the Pennsylvania Technical Guide.